Hurontario LRT Construction Update

The following is an update from Metrolinx, please visit their website for more information:

http://www.metrolinx.com/en/greaterregion/projects/hurontario-lrt.aspx

As part of the ongoing preparatory construction works along the Hurontario LRT corridor, Enbridge Gas Distribution has started to relocation works in the following areas.

Enbridge crews mobilized on Centre View Drive, between Duke of York Boulevard and City Centre Drive on October 22nd. Work is expected to last approximately 9 weeks, finishing in mid-December. During this time, eastbound lanes on Centre View Drive will be reduced to ensure crews can safely carry out work. For more information, please review the construction notice on our website.

Enbridge crews will be onsite, starting at the intersection of John Street and Huriontario Street starting in early November. Work will progress towards Dundas Street over the course of 4 months, with a completion date expected by end of March, 2019.

During this time, lane reductions will be required along Hurontario Street to ensure crews can safely carry out work. The amount of lanes reductions will depend on the work being carried out. For updated information on lane reductions and access to businesses in this area, please follow us on Twitter and review the construction notice on our website.

Enbridge crews mobilized on King Street East and Shepard Avenue in mid-November.. Work is expected to last approximately 4 weeks, finishing in mid-December. During this time, lanes will be reduced along both King Street East and Shepard Avenue to ensure crews can safely carry out work. For more information, please review the construction notice on our website.